Lavender Bay

Please click on image to see full image

Scope of Works:
Demolition, bulk excavation of 3500m³ and detailed excavation of lift pit, retention tank, footings and trenches.
 
Site Notes:
The site had an existing 2 storey dwelling and detached garage, which was demolished. The site has been scrubbed of all vegetation and top soil to make way for a bulk excavation of 3500m³ of sandstone.

 

Excavation method:

Bucket excavation of top soil, boundary rock sawing and hydraulic hammer excavation once in sandstone. 
 
Time on Site:
16 weeks including detailed excavations.

Sydney, NSW