Milson Rd, Cremorne Point

1/8

Please click on image to see full image

Scope of Works:
Demolition and Detailed Excavation of of 350m³ of footings and trenches.
 
Site Notes:
The site had a existing 2 storey apartment building, which was demolished. This site was unique as it came with an unusual challenge which included ramps over council land to mobilise and demobilise from the site. The works on site were only detailed excavation for the new building footprint. 

 

Excavation method:

Bucket excavation of top soil and hydraulic hammer excavation once in sandstone. 
 
Time on Site:
10 weeks including demolition.

Sydney, NSW